14 | Castellated Panel System
BaseTM Castellated Panel UFH System 16mm oxygen barrier pipework to install castellated panels in accordance with pipe layout design. Sand and cement/liquid screed/levelling compound to be installed (by others)
- Specification
- SYSTEM
- INSTALL
BaseTM Castellated Panel UFH System 16mm oxygen barrier pipework to install castellated panels in accordance with pipe layout design. Sand and cement/liquid screed/levelling compound to be installed (by others)
DOWNLOAD System Specification PDF
SYSTEM
- BaseTM Castellated Panel UFH System specifically designed for use within a screeded floor construction
- Installs directly to suitable rigid insulation panel to meet required thermal performance
- Offers design flexibility to accommodate irregular design layouts
- From 50mm castellated panel spacing allows flexible pipe layout to suit exact design requirements
INSTALL
- Rigid insulation required to subfloor in accordance with required thermal performance and current building regulations
- Perimeter expansion edging strip to be installed to perimeter with polymer staples ensuring polyethylene skirting is covering sub floor rigid insulation to prevent expansion of screed and thermal bridging
- Castellated panel to be installed directly to rigid sub floor insulation
- 16mm oxygen barrier pipe to be installed directly to castellated panel in continuous lengths from distribution manifold spaced according to underfloor heating design
- Pipework to be pressure tested and remain under pressure
- 65-75mm sand and cement screed / 50mm liquid screed / various levelling compound to be installed (by others)