  • BaseTM Castellated Panel UFH System specifically designed for use within a screeded floor construction
  • Installs directly to suitable rigid insulation panel to meet required thermal performance
  • Offers design flexibility to accommodate irregular design layouts
  • From 50mm castellated panel spacing allows flexible pipe layout to suit exact design requirements

INSTALL

  1. Rigid insulation required to subfloor in accordance with required thermal performance and current building regulations 
  2. Perimeter expansion edging strip to be installed to perimeter with polymer staples ensuring polyethylene skirting is covering sub floor rigid insulation to prevent expansion of screed and thermal bridging
  3. Castellated panel to be installed directly to rigid sub floor insulation 
  4. 16mm oxygen barrier pipe to be installed directly to castellated panel in continuous lengths from distribution manifold spaced according to underfloor heating design
  5. Pipework to be pressure tested and remain under pressure
  6. 65-75mm sand and cement screed / 50mm liquid screed / various levelling compound to be installed (by others)